BESCOM’s Scheduled Power Outages Maintenance Works in Bengaluru on May 29, 2024

Bengaluru July 27, 2024: A scheduled power outage is planned for Bangalore Elita Promenade Appartments,K.R Layout ,Sharadanagar, Chunchughatta And Area Surronding Sub-Station. on May 29,2024, from 10:00 to 15:00, with a total duration of 05:00 hours.. Tentative Line Clear/Outages Request for the month of May-2024 of Bengaluru Transmission Zone pertaining to BMAZ NORTH/SOUTH/BRAZ/CTAZ ZONE, BESCOM (Yet to be approved from BESCOM)  
Power Outage Attributes Details
Areas Affected Elita Promenade Appartments,K.R Layout ,Sharadanagar, Chunchughatta And Area Surronding Sub-Station.
Name of the KPTCL Circle BMAZ South
Name of the KPTCL Division 220kV Subramanyapura
Name of the BESCOM Zone BMAZ SOUTH
Name of the BESCOM Circle South
Name of the BESCOM Division Jayanagar
Name of the station/Line 66/11KV Elita Promonade muss
Date 5/29/2024
Time from 10:00
Time To 15:00
Duration 5:00
Reason for availing LC 11KV Bus, Tr-1 Bank, 11KV Bus maintenance of Bank-
Date on which last LC was availed 20.12.2024
Load Affected (MW) 3
Weather alternate Power Supply Arranged 3MW load can be shifted on nearby stations by BESCOM at the time of line clear
Remarks LC was proposed on 20.03.2024 but approval was not given.
Customer Support A 24X7 BESCOM Helpline is functioning in the premises of Corporate Office, Bengaluru. The Helpline Number is 1912
Source: BESCOM
See also  BESCOM's Scheduled Power Outages Maintenance Works in Bengaluru on May 18, 2024