BESCOM’s Scheduled Power Outages Maintenance Works in Bengaluru on May 22, 2024

Bengaluru July 27, 2024: A scheduled power outage is planned for Bangalore Maruthi Sevanagar, Jai Bharath Nagar, Frazer Town , Cox Town, Benson Town, Richards Town, Davis Road, Mosque Road, Biyappana Halli, Nagena Palya, Lingaraj Puram, Halsoor, Jeevana Halli, R K Road, Coles Road Tanery Road, And Itc, Etc.. on May 22,2024, from 10:30 to 16:00, with a total duration of 05:30 hours.. Tentative Line Clear/Outages Request for the month of May-2024 of Bengaluru Transmission Zone pertaining to BMAZ NORTH/SOUTH/BRAZ/CTAZ ZONE, BESCOM (Yet to be approved from BESCOM)  
Power Outage Attributes Details
Areas Affected Maruthi Sevanagar, Jai Bharath Nagar, Frazer Town , Cox Town, Benson Town, Richards Town, Davis Road, Mosque Road, Biyappana Halli, Nagena Palya, Lingaraj Puram, Halsoor, Jeevana Halli, R K Road, Coles Road Tanery Road, And Itc, Etc..
Name of the KPTCL Circle BMAZ North
Name of the KPTCL Division Hebbal
Name of the BESCOM Zone BMAZ NORTH
Name of the BESCOM Circle Additional East Division
Name of the BESCOM Division E1,E2,E5
Name of the station/Line 66/11KV Pottery Road MUSS
Date 5/22/2024
Time from 10:30
Time To 16:00
Duration 5:30
Reason for availing LC 1. To carry out Maintenance work of incoming line, outgoing line, Transformer-1, Transformer-2 Bay, 66kV bus Gos, 11kV bus and breaker maintenance. 2. For reocrding the PI value of Retrofilled TR-1 20MVA
Date on which last LC was availed 18.01.2024
Load Affected (MW) 1. 8MW of load will be affected for 2 Hrs while carrying out transformer- 2 maintenance 2. 25MW of load will be effected for 3 Hrs during bus & PT maintainence
Weather alternate Power Supply Arranged Peak Load of Station is 30 MW, Load change over of 6MW shall be done by BESCOM to neighboring stations 1. During LC period of Transformer-1 (2 Hrs)- Peak load is 14MW Transformer-2 (31.5 MVA) will be in charge condition and the load of transformer-1 will be catered on transformer-2 by using bus coupler. No load will be effected. 2. During LC period of Transformer-2 (2 Hrs)- Peak load is 16 MW Transformer -1 (20 MVA) will be in charge condition and the load of transformer-2 will be catered on transformer-1 by using bus coupler. During this period around 8 MW of load shedding will be carried out. 3. 6 MW of load will be affected for 2 Hrs while carrying out transformer- 2 maintenance. 4. 26MW of load will be effected for 3hrs during 66kV & 11kV bus & PT maintainence.
Remarks
Customer Support A 24X7 BESCOM Helpline is functioning in the premises of Corporate Office, Bengaluru. The Helpline Number is 1912
Source: BESCOM