BESCOM’s Scheduled Power Outages Maintenance Works in Bengaluru on May 18, 2024

Bengaluru July 4, 2024: A scheduled power outage is planned for Bangalore Ias Colony,Kas Colony,Ns Palya Industrial Area, Jhanvi Enclave,Ananth Layout Bilekahalli Village,Bilekahalli Main Road,4Th T Block Jaynagar,9Th Block Jayngar,East End Abcd Road,Bhel Layout,Srk Gardens,Nal Layout,Tilak Nagar,9Th Block Jayanagar,Partial 4Th T Block,Shanthi Park And Apartment,Jayadeva Hospital,Ranka Colony Road And Surrounding,Ns Palya Main Road,Grb Main Road,Jain Temple Road,Some Parts Of Btm 4Th Stage, Vaishya Bank Colony,Btm 2Nd Stage,Mchs Layout,Bhcs Layout,Shantiniketan School,Mico Layout,7Th Main, Mantri Apartment, & Surrounding Areas,Oracle,Ibm & Spar, Gurappanapalya Full Area,Timber Galli Road,Bismillah Nagar,Shobha Apartments,Divyashree Towers,Vega City Mall,Airtel Office,Bannerghatta Main Road & Surrounding,Keb Colony, Ne Gurappanapalya , Btm 1St Stage & Surroundings. on May 18,2024, from 10:00 to 16:00, with a total duration of 06:00 hours.. Tentative Line Clear/Outages Request for the month of May-2024 of Bengaluru Transmission Zone pertaining to BMAZ NORTH/SOUTH/BRAZ/CTAZ ZONE, BESCOM (Yet to be approved from BESCOM)  
Power Outage Attributes Details
Areas Affected Ias Colony,Kas Colony,Ns Palya Industrial Area, Jhanvi Enclave,Ananth Layout Bilekahalli Village,Bilekahalli Main Road,4Th T Block Jaynagar,9Th Block Jayngar,East End Abcd Road,Bhel Layout,Srk Gardens,Nal Layout,Tilak Nagar,9Th Block Jayanagar,Partial 4Th T Block,Shanthi Park And Apartment,Jayadeva Hospital,Ranka Colony Road And Surrounding,Ns Palya Main Road,Grb Main Road,Jain Temple Road,Some Parts Of Btm 4Th Stage, Vaishya Bank Colony,Btm 2Nd Stage,Mchs Layout,Bhcs Layout,Shantiniketan School,Mico Layout,7Th Main, Mantri Apartment, & Surrounding Areas,Oracle,Ibm & Spar, Gurappanapalya Full Area,Timber Galli Road,Bismillah Nagar,Shobha Apartments,Divyashree Towers,Vega City Mall,Airtel Office,Bannerghatta Main Road & Surrounding,Keb Colony, Ne Gurappanapalya , Btm 1St Stage & Surroundings.
Name of the KPTCL Circle BMAZ South
Name of the KPTCL Division HSR Layout
Name of the BESCOM Zone BMAZ SOUTH
Name of the BESCOM Circle South
Name of the BESCOM Division Jayanagar, Koramangala,BTM & Hulimaavu
Name of the station/Line 66/11KV Jayadeva S/s
Date 5/18/2024
Time from 10:00
Time To 16:00
Duration 6:00
Reason for availing LC 1)Periodical Quarterly-4 Maintenance work of 66/11kV Transformers, 66kV Isolators,66kV CT’s & PT’s 2)11kV Switchgears maintenance
Date on which last LC was availed 20.01.2024
Load Affected (MW) Peak load-35MW, Load change over-8MW, Load affected-27MW
Weather alternate Power Supply Arranged Arrangement can be done from BESCOM end through changeovers for load of about 8MW
Remarks Periodical 1ST Quarterly maintenance work 2024-25
Customer Support A 24X7 BESCOM Helpline is functioning in the premises of Corporate Office, Bengaluru. The Helpline Number is 1912
Source: BESCOM
See also  BESCOM's Scheduled Power Outages Maintenance Works in Bengaluru on May 20, 2024