Bengaluru July 14, 2024: A scheduled power outage is planned for Bangalore Mykonos Block 3&4, Mykonos Block 2, Club House , Santorini-2, Block 10,Serenita Block 13, Paradiso Block 3, Block 17, Brigade Northridge, Sampigehalli Police Station. Chokkanahalli Layout, Basavalingappanagara, Hegdenagar, Balaji Krupa Layout, Central Exuse Layout, Central Revenue Layout,Shiridi Sai Ram Layout,Bds Layout,Railway Main Layout, Thirumenahalli, Bharathicity,Nandanavana Layout, Manipal, Police Quarters, Kempegowda Layout, Nagenahalli, Knp Layout, Royalbenz,Devils Paradise, Hujbhavan on May 29,2024, from 11:00 to 16:00, with a total duration of 05:00 hours.. Tentative Line Clear/Outages Request for the month of May-2024 of Bengaluru Transmission Zone pertaining to BMAZ NORTH/SOUTH/BRAZ/CTAZ ZONE, BESCOM (Yet to be approved from BESCOM)  
Power Outage Attributes Details
Areas Affected Mykonos Block 3&4, Mykonos Block 2, Club House , Santorini-2, Block 10,Serenita Block 13, Paradiso Block 3, Block 17, Brigade Northridge, Sampigehalli Police Station. Chokkanahalli Layout, Basavalingappanagara, Hegdenagar, Balaji Krupa Layout, Central Exuse Layout, Central Revenue Layout,Shiridi Sai Ram Layout,Bds Layout,Railway Main Layout, Thirumenahalli, Bharathicity,Nandanavana Layout, Manipal, Police Quarters, Kempegowda Layout, Nagenahalli, Knp Layout, Royalbenz,Devils Paradise, Hujbhavan
Name of the KPTCL Circle BMAZ North
Name of the KPTCL Division Hebbal
Name of the BESCOM Zone BMAZ NORTH
Name of the BESCOM Circle EAST
Name of the BESCOM Division Shivajinagar and Hebbal
Name of the station/Line 66/11KV Shobhacity
Date 5/29/2024
Time from 11:00
Time To 16:00
Duration 5:00
Reason for availing LC 1. To carry out Maintenance work of incoming line, outgoing line, Transformer Bays, 66kV bus Gos,11kV bus and breaker maintenance. 2. For carrying out IR test of all equipements like CT’s, PT’s, LA’s, Transformers, 66kV Breakers, 11kV Breakers, Wall entry bushings and 11kV Bus.
Date on which last LC was availed 21.11.2023
Load Affected (MW) 21 MW load will be affected for 3hrs while carrying out 11kV Bus & 66kV Bus Maintenance work
Weather alternate Power Supply Arranged Peak load of station is :21MW transformer1 is 11 MW & transformer 2 is 11 MW 1)While carrying out Tr-1 maintenance, Transformer2 will be in charge condition load of Tr-1, will be shifted on Tr-2 using Bus Coupler. 2)While carrying out Tr-2 maintenance ,Transformer1 will be in charge condition load of Tr-2 ,will be shifted on Tr-1 using Bus Coupler. 3) During LC period 5MW of load will be changed over by BESCOM. 4) Duing 66&11kv bus maintainance 21 MW of load will be affected for 3 hrs (station shutdown).
Remarks
Customer Support A 24X7 BESCOM Helpline is functioning in the premises of Corporate Office, Bengaluru. The Helpline Number is 1912