Power Outage Attributes | Details |
---|---|
Areas Affected | Bescom Kudur Subdivision Area Feeding From Hullenahalli Substation , Neralekere, Gangonahalli, Tippasandra, Hullenahalli, Tavarekere, Sankigatta, Honnapura, Virupapura, Sugganahalli, Hebalalu, Beechanahalli And Chikkanahalli |
Name of the KPTCL Circle | Ramanagara |
Name of the KPTCL Division | Nelamangala |
Name of the BESCOM Zone | BRAZ |
Name of the BESCOM Circle | Ramanagara |
Name of the BESCOM Division | Magadi |
Name of the station/Line | 66/11KV Hullenahalli |
Date | 5/22/2024 |
Time from | 10:00 |
Time To | 15:00 |
Duration | 5:00 |
Reason for availing LC | LC availed for Quartely maintenance |
Date on which last LC was availed | 26.11.2023 |
Load Affected (MW) | 10 |
Weather alternate Power Supply Arranged | NO |
Remarks | |
Customer Support | A 24X7 BESCOM Helpline is functioning in the premises of Corporate Office, Bengaluru. The Helpline Number is 1912 |
BESCOM’s Scheduled Power Outages Maintenance Works in Bengaluru on May 22, 2024
Bengaluru July 7, 2024: A scheduled power outage is planned for Bangalore Bescom Kudur Subdivision Area Feeding From Hullenahalli Substation , Neralekere, Gangonahalli, Tippasandra, Hullenahalli, Tavarekere, Sankigatta, Honnapura, Virupapura, Sugganahalli, Hebalalu, Beechanahalli And Chikkanahalli on May 22,2024, from 10:00 to 15:00, with a total duration of 05:00 hours.. Tentative Line Clear/Outages Request for the month of May-2024 of Bengaluru Transmission Zone pertaining to BMAZ NORTH/SOUTH/BRAZ/CTAZ ZONE, BESCOM (Yet to be approved from BESCOM)
Source: BESCOM