Bengaluru July 23, 2024: A scheduled power outage is planned for Bangalore Bwssb Stp, Jakkasandra, Hsr 5Th Sector Teachers Colony, Part Of Venkatapura, Greenage Apartment, Koramangala Extention on May 22,2024, from 10:00 to 15:00, with a total duration of 05:00 hours.. Tentative Line Clear/Outages Request for the month of May-2024 of Bengaluru Transmission Zone pertaining to BMAZ NORTH/SOUTH/BRAZ/CTAZ ZONE, BESCOM (Yet to be approved from BESCOM)  
Power Outage Attributes Details
Areas Affected Bwssb Stp, Jakkasandra, Hsr 5Th Sector Teachers Colony, Part Of Venkatapura, Greenage Apartment, Koramangala Extention
Name of the KPTCL Circle BMAZ South
Name of the KPTCL Division HSR Layout
Name of the BESCOM Zone BMAZ SOUTH
Name of the BESCOM Circle South
Name of the BESCOM Division HSR Layout & Koramangala
Name of the station/Line 66/11KV Jakkasandra S/s
Date 5/22/2024
Time from 10:00
Time To 15:00
Duration 5:00
Reason for availing LC 1. Periodical Maintenance work (1st Quarterly) of 1x20MVA Tr’s, Bus GOS, line GOS, 66kV Breakers, 66kV CT’s and 66kV PT’s. 2. Periodical Maintenance work of 11kV switchgears
Date on which last LC was availed 24.01.2024
Load Affected (MW) Peak load-10.0MW, Load change over-9.0MW, Load affected-1MW 01 MW load affected from 10:00 to 15:00 Hrs, due to there is only one Bank
Weather alternate Power Supply Arranged Load Change Over-9.0 MW by BESCOM
Remarks Periodical 1st Quarterly maintenance work.
Customer Support A 24X7 BESCOM Helpline is functioning in the premises of Corporate Office, Bengaluru. The Helpline Number is 1912
Source: BESCOM