Bengaluru July 7, 2024: A scheduled power outage is planned for Bangalore A. Areas Feeding From Down Streams Of 220/66/11Kv R/S Dabaspet. 1.66/11 Kv Nelamangala 2. 66/11 Kv Thyamagondlu 3. 66/11 Kv T Begur 4. 66/11 Kv Hirehalli 5. 66/11 Kv Averahalli 5. 66/11 Kv S K Steel(Eht) 6. 66/11 Kv Jindal(Eht). B. Dabaspet Sub Division Area Feeding From 1.220/66/11Kv R/S Dabaspet on May 19,2024, from 10:00 to 17:00, with a total duration of 07:00 hours.. Tentative Line Clear/Outages Request for the month of May-2024 of Bengaluru Transmission Zone pertaining to BMAZ NORTH/SOUTH/BRAZ/CTAZ ZONE, BESCOM (Yet to be approved from BESCOM)  
Power Outage Attributes Details
Areas Affected A. Areas Feeding From Down Streams Of 220/66/11Kv R/S Dabaspet. 1.66/11 Kv Nelamangala 2. 66/11 Kv Thyamagondlu 3. 66/11 Kv T Begur 4. 66/11 Kv Hirehalli 5. 66/11 Kv Averahalli 5. 66/11 Kv S K Steel(Eht) 6. 66/11 Kv Jindal(Eht). B. Dabaspet Sub Division Area Feeding From 1.220/66/11Kv R/S Dabaspet
Name of the KPTCL Circle Ramanagara
Name of the KPTCL Division Nelamangala
Name of the BESCOM Zone BRAZ
Name of the BESCOM Circle Bangalore
Name of the BESCOM Division Nelamangala
Name of the station/Line 220/66/11 kv R/S Dabaspet
Date 5/19/2024
Time from 10:00
Time To 17:00
Duration 7:00
Reason for availing LC Quarterly maintenance of 220/66/11kv R/S Dabaspet for FY-2024-25.. 1. 220kv and 66kv bus-preventive Maintenance and attending critical hotspots. 2. 100MVA TR1 & 150 MVA TR2- 1st Quaterly and Annual preventive maintenance and attending critical hotspot observation. 3. 31.5MVA TR1 & TR2- 1 st Quaterly and Annual preventive maintenance and attending critical hotspot observation. 4. 220kv and 66kv Line bays-1 st Quaterly and Annual preventive maintenance and attending critical hotspot observation. 5. 11kv GOS- 1 st Quaterly and Annual preventive maintenance and attending critical hotspots, replacement of 11kv feeders GOS contacts, weaken jumps and pothead repair work.
Date on which last LC was availed 10.12.2023
Load Affected (MW) 190MW
Weather alternate Power Supply Arranged No
Remarks
Customer Support A 24X7 BESCOM Helpline is functioning in the premises of Corporate Office, Bengaluru. The Helpline Number is 1912