Planned Power Outages in Bengaluru BESCOM Works MAY-2024 Devanahalli, Vijayapura

BESCOM’s Scheduled Power Outages Maintenance Works in T Begur Substation Bengaluru on May 19, 2024

Bengaluru July 6, 2024: A scheduled power outage is planned for Bangalore 11Kv Feeders Evacuating From 66/11Kv T Begur Substation Coming Under Nelamangala And Dabaspet Subdivisions, Bescom on May 19,2024, from 10:00 to 17:00, with a total duration of 07:00 hours.. Tentative Line Clear/Outages Request for the month of May-2024 of Bengaluru Transmission Zone pertaining to BMAZ NORTH/SOUTH/BRAZ/CTAZ ZONE, BESCOM (Yet to be approved from BESCOM)  
Power Outage Attributes Details
Areas Affected 11Kv Feeders Evacuating From 66/11Kv T Begur Substation Coming Under Nelamangala And Dabaspet Subdivisions, Bescom
Name of the KPTCL Circle Ramanagara
Name of the KPTCL Division Nelamangala
Name of the BESCOM Zone BRAZ
Name of the BESCOM Circle Bangalore
Name of the BESCOM Division Nelamangala
Name of the station/Line 66/11kv Substation T Begur
Date 5/19/2024
Time from 10:00
Time To 17:00
Duration 7:00
Reason for availing LC LC availed for Quartely maintenance
Date on which last LC was availed 10.12.2023
Load Affected (MW) 22MW
Weather alternate Power Supply Arranged No
Remarks
Customer Support A 24X7 BESCOM Helpline is functioning in the premises of Corporate Office, Bengaluru. The Helpline Number is 1912
Source: BESCOM
See also  BESCOM's Scheduled Power Outages Maintenance Works in Bengaluru on May 29, 2024