Bengaluru September 14, 2024: A scheduled power outage is planned for Bangalore Rt Nagar, Ganga Nagar,Cholanagar, Outer Ring Road,Kariyappalayout,Ashram Road, 1St Block Anandnagar Guddappareddy Layout, Hebbal, Jayamahal 1St Block, Nandidurga Road, Marappa Garden, Jcnagar,Millers Road Ganga Nagar ,Chamundhi Nagar,Dinnur,P&T Colony ,Ex Service Men Colony ,Mla Layout,Gananagar Extension ,Rbi Colony,Hmt Layout ,Vasanthappa Block Etc on May 14,2024, from 11:00 to 16:00, with a total duration of 05:00 hours.. Tentative Line Clear/Outages Request for the month of May-2024 of Bengaluru Transmission Zone pertaining to BMAZ NORTH/SOUTH/BRAZ/CTAZ ZONE, BESCOM (Yet to be approved from BESCOM)  
Power Outage Attributes Details
Areas Affected Rt Nagar, Ganga Nagar,Cholanagar, Outer Ring Road,Kariyappalayout,Ashram Road, 1St Block Anandnagar Guddappareddy Layout, Hebbal, Jayamahal 1St Block, Nandidurga Road, Marappa Garden, Jcnagar,Millers Road Ganga Nagar ,Chamundhi Nagar,Dinnur,P&T Colony ,Ex Service Men Colony ,Mla Layout,Gananagar Extension ,Rbi Colony,Hmt Layout ,Vasanthappa Block Etc
Name of the KPTCL Circle BMAZ North
Name of the KPTCL Division Hebbal
Name of the BESCOM Zone BMAZ NORTH
Name of the BESCOM Circle North
Name of the BESCOM Division C4,C5,C2 benson down
Name of the station/Line 220/66/11 KV Hebbal
Date 5/14/2024
Time from 11:00
Time To 16:00
Duration 5:00
Reason for availing LC 1. To carry out Maintenance work of 2*20 MVA ,1*31.5 MVA Transformer, 66kV bus Gos,11kV bus and breaker maintenance. 2. For attending Hotspot works. 3. For carrying out IR test of all equipements like CT’s, PT’s, LA’s, Transformers, 66kV Breakers, 11kV Breakers, Wall entry bushings and 11kV Bus. 4. For conducting Tan-Delta on all 66kV CT’s
Date on which last LC was availed 26/09/2023
Load Affected (MW) 13 MW will be affected during LC period of 20MVA Tr-1 & 2 19MW will be affected during LC period of 31.5MVA Tr-3
Weather alternate Power Supply Arranged Peak load of the station 45 MW,1)The transformer-1 20 MVA lc shall be availed from 11:00hrs to 12:30 hrs during this lc period load 13 mw load will be affected and Trasformer-2 and Transformer-3 will be in charge condition 2) The Transformer 2 lc shall be availed from 12:30 to 14:00 hrs and 13 mw load shall be affected , transfomer 1 and transformer 3 will be in charge condition 3) Transformer-3 lc shall be availed from 14:00 hrs to 16:00 hrs and 19mw will be affected , transfomer 1 and transformer 2 will be in charge condition
Remarks
Customer Support A 24X7 BESCOM Helpline is functioning in the premises of Corporate Office, Bengaluru. The Helpline Number is 1912
Source: BESCOM
See also  BESCOM's Scheduled Power Outages Maintenance Works in Bengaluru on May 22, 2024

Leave a Reply

Your email address will not be published. Required fields are marked *