BESCOM’s Scheduled Power Outages Maintenance Works in Bengaluru on May 13, 2024

Bengaluru July 22, 2024: A scheduled power outage is planned for Bangalore Purvankara Apartment, Gavigudi, Kalkere Road, Poorna Pragnya, Maragondanahalli, Halehalli, Byrathi Village, Byrathi Bande,Kanakashree Layout, Kyalasanahalli on May 13,2024, from 10:00 to 15:00, with a total duration of 05:00 hours.. Tentative Line Clear/Outages Request for the month of May-2024 of Bengaluru Transmission Zone pertaining to BMAZ NORTH/SOUTH/BRAZ/CTAZ ZONE, BESCOM (Yet to be approved from BESCOM)  
Power Outage Attributes Details
Areas Affected Purvankara Apartment, Gavigudi, Kalkere Road, Poorna Pragnya, Maragondanahalli, Halehalli, Byrathi Village, Byrathi Bande,Kanakashree Layout, Kyalasanahalli
Name of the KPTCL Circle BMAZ North
Name of the KPTCL Division Hebbal
Name of the BESCOM Zone BMAZ NORTH
Name of the BESCOM Circle E8,E9 sub division ,Additional East Shivajinagar division
Name of the BESCOM Division Shivajinagar & Hoskote division Division
Name of the station/Line 66/11KV Purvankara MUSS
Date 5/13/2024
Time from 10:00
Time To 15:00
Duration 5:00
Reason for availing LC 1. To carry out Maintenance work of incoming line, outgoing line, Transformer Bays, 66kV bus Gos,11kV bus and breaker maintenance. 2. For attending Hotspot works. 3. For carrying out IR test of all equipements like CT’s, PT’s, LA’s, Transformers, 66kV & 11kV Breakers, and 11kV Bus.
Date on which last LC was availed 9.11.2023
Load Affected (MW) 10MW load to be changed over by BESCOM for carrying out 11kV & 66kV Bus maintenance
Weather alternate Power Supply Arranged Peak load of station is 10MW,peak load of Tr1 is 4.3MW, Tr-2 is 6.7MW. 1) During LC period of Tr-1(12.5MVA) from 10:00 to 11:30, load of Tr-1 will be catered on Tr-2 through buscoupler and during this period no load will be affected. 2)During LC period of Tr-2(12.5MVA) from 11:30 to 13:00, load of Tr-2 will be catered on Tr-1 through buscoupler and during this period no load will be affected. 3) From 13:00 to 14:00 complete shutdown for 66kV bus maintenance, 10MW load to be changed over by BESCOM
Remarks
Customer Support A 24X7 BESCOM Helpline is functioning in the premises of Corporate Office, Bengaluru. The Helpline Number is 1912
Source: BESCOM
See also  BESCOM's Scheduled Power Outages Maintenance Works in Bengaluru on May 15, 2024